Infrastructure: Tender for Section 4 and Craiova-Pitesti Express Way resumed
The National Road Infrastructure Administration Corporation (CNAIR) lifted the suspension of tender procedure, offer presentation date being February 24
Companies willing to in participate in this public tender procedure can make clarification requests until the mentioned deadline that is 21 days before the presentation of offers.
The estimated value is 909,669,122 lei, without VAT. The contract will last 36 months: 12 months for design and 24 months for execution of works.
Section 4 is 31.81 km long (km 89+300 – km 121+115), will be built between the administrative limit between Olt and Arges and junction with highway 1 Bucharest-Pitesti and will cross territories of localities Lunca Corbului, Albota, Costesti, Bradu, Suseni and Oarja.